If your construction loan is paid in stages, each payment is called a drawdown. Before the lender releases the next one, an independent quantity surveyor typically confirms how much work has actually been completed. Here is how the process usually runs.

1. The builder issues a progress claim

The builder claims payment for work done to date. The claim may be based on stages (for example foundations, frame, lock-up, fit-out) or on a percentage of the total contract.

2. The claim goes to the QS

You (or your builder) send the claim to the quantity surveyor along with any approved variations since the last drawdown. The sooner this is done, the sooner funds can move.

3. The QS inspects the site

The QS visits the site, inspects the work in place and records it, usually with photos. The inspection is what separates a drawdown report from a desktop review: it ties the claim to what is physically there.

4. The QS values the work

The work in place is valued and compared with the amount claimed. If the claim is higher than the value of work completed, the difference is explained in the report.

5. Cost to complete is updated

The QS also checks the remaining cost against the remaining funds. This is the safeguard that tells the lender whether the project can still be finished with the money available.

6. The report goes to the lender

The lender uses the report to decide how much to release. Clear, timely reports usually mean faster payments for the builder and fewer disputes.

Tips for smoother drawdowns

  • Submit progress claims as soon as they are issued.
  • Make sure site access is arranged before the QS arrives.
  • Keep variations documented and approved in writing.
  • Raise any concerns early rather than at the final drawdown.